    new laneway costs?

    LOOKING AT CREATING A NEW FARM LANE = 800M LENGTH. light tractor traffic, any idea of costs? have no idea what to budget for this! gravel finish.

  2. #2
    Senior Member Quattromike's Avatar
    Join Date
    Feb 2013
    Location
    Moray
    Posts
    452

    Re: new laneway costs?

    What is the makeup of the proposed track, how much do you have to dig out to get to hard? Are you planning a contractor to come in clear the top soil dump elsewhere on the farm, buy in hardcore from quarry,level out shape road with slight camber roll it in. At a guess I'd say 25 /M
    "At the end of the day, I think it's going to get very dark."

  3. #3
    Senior Member
    Join Date
    Feb 2013
    Location
    Glamorgan
    Posts
    1,914

    Re: new laneway costs?

    Contractors around here got special attachement behind huge tractor to rotovate type of thing and then incorporate cement mix and does good job for tracks,pads etc

  4. #4
    Senior Member
    Join Date
    Feb 2013
    Location
    somerset now working in the real world
    Posts
    889

    Re: new laneway costs?

    Quote Originally Posted by jd 2650 View Post
    LOOKING AT CREATING A NEW FARM LANE = 800M LENGTH. light tractor traffic, any idea of costs? have no idea what to budget for this! gravel finish.
    Where abouts are you, there's a West Country firm call MP Goulding road stabilisation, they have a web site and do work all the uk, they have all manner of machines that will a track out of nowt,, inject mix in cement and leave a good jo so I've heard, no idea of cost,, but I suppose your only want to do once,,
    Big Vern..... Stay low Move faster

  5. #5
    Senior Member
    Join Date
    Feb 2013
    Posts
    480

    Re: new laneway costs?

    Lenth 800m

    Width? 3m?

    Depth of stone 0.2m?


    L x W x D 800 x 3 x 0.2 = 480m3

    Stone at 2ton per m3 = 960ton

    Stone at 10per ton = 9,600

    2 weeks for 13 ton track machine to strip soil, level stone and track in 80 hours at 40 hour = 3200


    Some fag packet figures, adjust them as you see fit.